Renovation Updates
Lunch and Dinner

2010 COURSE RENOVATION

03/12/2010 2:31 PM - Donny Darville, General Manager, Berry Creek
2010 Course Renovation

Green Sizes Example.jpg
Example of New Green Sizes
Average 50% increase
Front Nine Bunkers.gif
All Front Nine Bunkers are NOW
completed with new drainage


OVERVIEW

  • Start Date: No later than June 1 (this will be closely monitored for best start date)
  • Completed for play: Estimated between August 1 and August 31
  • Selected grass type: Mini Verde, an Ultradwarf Bermudagrass
CONSTRUCTION PROCESS
  • Construction time: 30 days (weather dependent)
  • Remove an average of 6” of existing sand on all greens including putting green
  • Add 6” of USGA conforming sand to all greens and till into existing mix
  • Increase total green surface from 76,166 sq. ft to 114,420 sq. ft. (50% increases to current sizes)
  • We will fumigate all greens to make sure all foreign grasses are cleaned
  • We will increase the greens contours and recapture some of the original design
  • We will be sprigging all the greens for seamless coverage
  • In-house work on other areas of the golf course as time and money allows (bunkers and other areas)
  • Grow in time of new grass estimated at 4-8 weeks
WHAT ABOUT PLAYING GOLF DURING THE RENOVATION?

  • Temporary greens will be used during most of the renovation
  • Extended hours of driving range
  • Area golf courses will allow are members to play at discounted rates (more details to come)
  • Additional fun golf events will be planned for members
BENEFITS OF YOUR NEW GREENS

  • No over seeding in winter
  • Little to no transition in spring
  • Faster putting surface
  • Larger putting surfaces for more pin placements